
The goal of the team members was to finish the roof of the 2nd floor of Hope School. The Africans were there to help also as the team worked for three weeks on the school.
The Steps of the Construction:
1. The boards for pouring concrete were clamped into place.

2. The ceiling blocks that were made previously by the Malians were taken upstairs.

3. The posts and boards were positioned in place in order to stablize the ceiling.

4. All the re-rod that was put together was positioned between the ceiling blocks.

5. The electrical conduit and wires for the ceiling lights were then placed.

6. Then the cement, gravel, and sand were mixed together by hand to make concrete.

7. The concrete was thrown up to the second floor by shovels rhythmically and then it was thrown to the roof.

8. The roof of the second floor was then leveled off by the team and Franklin.

9. The doors and windows for the three new classrooms have been purchased and have now been placed.







